电网技术2001,Vol.25Issue(1):34-37,4.
考虑机群出力约束的机组优化组合模型
A UNIT COMMITMENT APPROACH WITH POWER CONSTRAINTS
OF MACHINE GROUP
摘要
Abstract
In the operation of practical power system,the power output of some machine-group is restricted. A unit commitment model considering power constraints of machine-group is presented in this paper. The model is translated into a two-level single object decision-making problem with leader-follower strategy with no relation between lower levels. The leader problem is a classical unit commitment problem, while the aim of the lower problems is to minimize the modified-quantity of utmost output value of the generators. The
coordinating algorithm of lead-problem and lower problems isput forward. The effectiveness and practicability of this
approach are proved by the experience of applying the
approach to Jilin power system.关键词
机组组合/主从递阶/机群分类
信息技术与安全科学引用本文复制引用
王鹏,李国辉,张粒子,贺仁睦..考虑机群出力约束的机组优化组合模型[J].电网技术,2001,25(1):34-37,4.