Abstract
Based on the investigation of current status of the cellar construction project for water harvesting in loess plateau of china. It is pointed out that the existed problem in the project, which included of superfluous of cellars along the supperways and roadways, shortage of ground for water producing, and also problems in cellar construction and sand sinking pound. According to the analysis of potential water harvested and water needed for human and livestock and irrigation, a system of cellar quota is given for the along road cellar construction. And also, some countermeasures to well build the cellar water harvesting system and better sand sinking pound are recommended.关键词
窑窖建设/窑窖规划/沉沙池/黄土高原引用本文复制引用
史慧珍,徐学选,张世彪..黄土高原窑窖集水工程技术探讨[J].水土保持通报,2001,21(2):45-47,3.