水利水电科技进展2001,Vol.21Issue(1):47-48,52,3.
李家峡导流隧洞快速掘进施工中的新技术
New Technology in Construction of Lijiaxia DiversionTu mna with High- Speed Drivage
摘要
Abstract
The geological condition of the diversion tunnelof Lijiaxia Hydropower Station is very complicated.During construction, the suspended crown concrete liningtechnique of the “New Austrian Tunneling Method” wassuccessfully used for the first time in China. Theconstruction technologies such as overlapping excavation,overlapping placement and so on have been developed andapplied with a good result. The collapses in the diversion tunnel under weak geological conditions have been controlled to a maximum, and the advance speed of largesection diversion tunnel has been raised to a high level in China.
关键词
导流洞/软弱地质/支护/错缝开挖/错缝浇筑/李家峡水电站分类
建筑与水利引用本文复制引用
张光敏..李家峡导流隧洞快速掘进施工中的新技术[J].水利水电科技进展,2001,21(1):47-48,52,3.