李家峡导流隧洞快速掘进施工中的新技术

New Technology in Construction of Lijiaxia DiversionTu mna with High- Speed Drivage

张光敏1

作者信息

  • 1. 中国水利水电第四工程局,
  • 折叠

摘要

Abstract

The geological condition of the diversion tunnelof Lijiaxia Hydropower Station is very complicated.During construction, the suspended crown concrete liningtechnique of the “New Austrian Tunneling Method” wassuccessfully used for the first time in China. Theconstruction technologies such as overlapping excavation,overlapping placement and so on have been developed andapplied with a good result. The collapses in the diversion tunnel under weak geological conditions have been controlled to a maximum, and the advance speed of largesection diversion tunnel has been raised to a high level in China.

关键词

导流洞/软弱地质/支护/错缝开挖/错缝浇筑/李家峡水电站

分类

建筑与水利

引用本文复制引用

张光敏..李家峡导流隧洞快速掘进施工中的新技术[J].水利水电科技进展,2001,21(1):47-48,52,3.

水利水电科技进展

1006-7647

访问量0
|
下载量0
段落导航相关论文