Treatment to Defects of Tunnel No.6 to No.8 Constructed by TBM in Main Trunk Line of YRDP

赵廷式1

作者信息

  • 1. 山西省万家寨引黄工程管理局,
  • 折叠

摘要

Abstract

Double-shield Tunnel Boring Machine (TBM) and honeycomb segment design are not fit for the construction under some unfavorable geological conditions, such as earth section, fracture zone of fault, karst and swelling rock etc. However, these unfavorable conditions are usually unavoidable during the construction of long tunnel. Effective defect treatment is the only way to ensure safe tunnle operation. Thus, this kind of TBM can be used in a more extensive area. TBM construction method was adopted in No.6, No.7 and No.8 tunnels of main trunk Line of Wanjiazhai Yellow River Diversion Project for passing through Q2 an Q3 loess section and N2 red clay section. This paper provides detailed description of the quality defects encountered and relevant dealing measures.

关键词

万家寨引黄工程/TBM掘进机/Q2、Q3黄土/N2红粘土

分类

建筑与水利

引用本文复制引用

赵廷式..万家寨引黄工程总干线#6、#7、#8隧洞TBM施工缺陷处理[J].水利水电技术,2001,32(4):4-8,5.

水利水电技术

OA北大核心

1000-0860

访问量0
|
下载量0
段落导航相关论文