锦江水电厂机组增容改造的实践
Capacity-increasing transformation of hydro gener ating units of Jinjiang Hydropower Station
摘要
Abstract
Many cracks were found in the impellers of Unit 1 and 2 inJinjiang Hydropower Station, which exposed some of the blades to the risk of fracture and seriously threatened the safety operation of the station. Through calculation and investigation, a capacity-increasing transformation plan was determined, i.e., to replace the original impellers with proof stainless steel ones, and raise the unit output to 15.4 MW after the new impellers satisfy the requirements. Satisfactory results were obtained after the transformation.关键词