Abstract
According to shield construction of Nanjing Yangtze river tunnel project, this paper analyses the causes leading to shield tail leakage in shield construction, and the pertinence prevention measures as well as emergency plans are also proposed to ensure the shield construction salty of Nanjing Yangtze river tunnel.关键词
过江隧道/盾构施工/盾尾泄漏/原因分析/预防措施Key words
cross-river tunnel/shield construction/shield tail leakage/reason analysis/prevention measures分类