港工技术2011,Vol.48Issue(1):41-43,3.
低位真空预压法吹填土软基加固技术的应用
Application of Low Vacuum Preloading on Dredger Fill Soft Foundation Consolidation
方子杰 1应舒2
作者信息
- 1. 浙江省围垦技术中心,浙江,杭州,310014
- 2. 温州经济技术开发区基础设施投资有限公司,浙江,温州,325000
- 折叠
摘要
Abstract
After reclamation of tidal flat is made,the fenced area is backfilled firstly to elevate the level ground.As the backfilling option is decided,the problems such as the source of backfill material and foundation treatment way should be considered emphatically.The technology of low vacuum preloading on dredger fill soft foundation is the one of relatively mature with the low cost,short construction period and less impact on the surrounding environment and it is convenient to expropriate land in the future.The method is an appropriate choice to consolidate the dredger fill soft foundation in a shorter construction period.关键词
围区回填/地基处理/低位真空预压法/吹填土Key words
fenced area backfilling/foundation treatment/low vacuum preloading method/dredger fill分类
建筑与水利引用本文复制引用
方子杰,应舒..低位真空预压法吹填土软基加固技术的应用[J].港工技术,2011,48(1):41-43,3.