The fluid-structure coupling vibration model based on overall turbulence-structure of powerhouse in Luding Hydropower Station is established for analyzing the coupled vibration of flow passage, powerhouse concrete structures and generating units.The time response of powerhouse coupling vibration on design operating duty is calculated, and as a basis,the overall vibration of the powerhouse is analyzed.The simulations show that the vibrations of overall powerhouse and local components can meet the requirements of specifications.

关键词

水电站厂房/振动/流固耦合/振源特性/响应/泸定水电站

分类

建筑与水利

引用本文复制引用

陈东升,尹葵霞,王建玲..大渡河泸定水电站厂房振动分析[J].水力发电,2011,(5):29-33,5.