Taking the project of Hongjiadu CFRD as an example, on the base of nonlinear DFuncanchang E-B model, the paper established the finite element model.By using midpoint incremental method, aim at the two conditions of whether to use temporary section retaining water in construction period,discussed the temporary section retaining water for dam deformation and stress influence under the conditions of dam completion period stress deformation and stress influence under the conditions of dam completion period stress deformation calculation and comparison.Results showed than the influence of the mporary section retaining water dam deformation and stress of completion period is limited, using provisional cross-section retaining water flood construction scheme is feasible.关键词
混凝土面板堆石坝/临时断面/挡水/应力变形/非线性Key words
CFRD/ temporary cross-section/ water retaining/ stress-strain/ non-linear分类
建筑与水利引用本文复制引用
崔自力,王瑞骏,付国栋,薛霄,陈前玲..临时断面挡水度汛对面板堆石坝应力变形的影响分析[J].水资源与水工程学报,2011,22(2):132-136,5.