| 注册
首页|期刊导航|压力容器|延迟焦化装置中带碟簧的管法兰接头三维数值分析

延迟焦化装置中带碟簧的管法兰接头三维数值分析

董智 仇性启 赵宗彬

压力容器2011,Vol.28Issue(5):15-20,6.
压力容器2011,Vol.28Issue(5):15-20,6.DOI:10.3969/j.issn.1001-4837.2011.05.003

延迟焦化装置中带碟簧的管法兰接头三维数值分析

Three-Dimensional Numerical Analysis for the Pipe Flanged Jiont with Belleville Spring in Delayed Coking Unit

董智 1仇性启 1赵宗彬1

作者信息

  • 1. 中国石油大学(华东)机电工程学院,山东青岛,266555
  • 折叠

摘要

Abstract

FEA was used to analyze the force and deformation of coke tower and the pipe in delayed coking unit. Three - dimensional numerical analysis for the pipe flanged joint with belleville spring was carried on to investigate belleville spring's effects on gasket stress under the elevated temperature condition of coking stage. The results of the simulation show that coke tower produces thermal expansion, so induces the bend deformation of pipeline in the coking stage. High temperature's effects on them are more obvious than the pressure's. Proper use of belleville spring is more favourable for maintaining the working stress of gasket of the pipe flanged joint under the condition of elevated temperature.

关键词

有限元/延迟焦化/高温/碟形弹簧/垫片应力

Key words

FEA/delayed coking/elevated temperature/belleville spring/gasket stress

分类

机械制造

引用本文复制引用

董智,仇性启,赵宗彬..延迟焦化装置中带碟簧的管法兰接头三维数值分析[J].压力容器,2011,28(5):15-20,6.

压力容器

OACSTPCD

1001-4837

访问量0
|
下载量0
段落导航相关论文