旁多水利枢纽砂砾石坝壳料现场碾压质量控制曲线
Quality control curve for field rolling of gravel materials of earth-rockfill dams in Pangduo Hydraulic Project
向尚君 1赵兴安 1邱炽兴 1吴涛 1林光跃1
作者信息
- 1. 中国人民武装警察部队水电第三总队,四川成都,610036
- 折叠
摘要
Abstract
At present, there still is a lack of a complete and mature method to determine the maximum dry density in relative density tests on filling and rolling of gravel materials. Based on rolling tests on gravel materials of Pangduo Hydraulic Project, the compacted dry density of the gravel materials after 20 times of rolling and strong vibration by use of a 20-tonnage vibratory roller was regarded as the maximum dry density. The relation curves for the maximum dry density, the minimum dry density and the mass fraction of gravel rnaterials were derived by means of the mathematical analysis software. The quality control curve for the field rolling of gravel materials was finally determined according to the control indices for the relative density.关键词
土石坝/砂砾石料/最大干密度/质量控制曲线/旁多水利枢纽Key words
earth-rockfill dam/ gravel material/ maximum dry density/ quality control curve/ Pangduo Hydraulic Project分类
建筑与水利引用本文复制引用
向尚君,赵兴安,邱炽兴,吴涛,林光跃..旁多水利枢纽砂砾石坝壳料现场碾压质量控制曲线[J].水利水电科技进展,2011,31(3):92-94,3.