向家坝-上海±800kV特高压直流输电工程系统调试技术分析

杨万开 印永华 曾南超 王华伟 王明新 张健

电网技术2011,Vol.35Issue(7):19-23,5.
电网技术2011,Vol.35Issue(7):19-23,5.

向家坝-上海±800kV特高压直流输电工程系统调试技术分析

Analysis on Commissioning Test of±800 kV UHVDC Transmission Project from Xiangjiaba to Shanghai

杨万开 1印永华 1曾南超 1王华伟 1王明新 1张健1

作者信息

  • 1. 中国电力科学研究院,北京市海淀区100192
  • 折叠

摘要

Abstract

The commissioning test of ±800 kV DC transmission project from Xiangjiaba to Shanghai, which was the longest distance UHVDC transmission system with the largest capacity in the world up to now, was presented,including the calculation and analysis of the system, its commissioning scheme, the drafting of implementation schedule for system commissioning and circumstances during on-site system commissioning. The test items completed in stages during on-site commissioning were classified, and the test results of items belonging to each test category were analyzed and corresponding conclusions were given. Main technical problems appearing during the commissioning,especially the problems that were found during monopole high power test, were analyzed in detail, and the solution of these problems guaranteed the commissioning going on wheels and putting into operation on time.

关键词

特高压直流输电工程/系统调试/系统安全稳定计算分析/现场调试实施计划编写

Key words

UH-VDC project/ commissioning test/calculation and analysis of system security and stability/drafting of implementation schedule for on-site commissioning

分类

信息技术与安全科学

引用本文复制引用

杨万开,印永华,曾南超,王华伟,王明新,张健..向家坝-上海±800kV特高压直流输电工程系统调试技术分析[J].电网技术,2011,35(7):19-23,5.