糯扎渡水电站泄洪洞底拱混凝土滑模施工技术

张尹耀 李文瑛 宋希宁

水力发电2011,Vol.37Issue(7):47-49,3.
水力发电2011,Vol.37Issue(7):47-49,3.

糯扎渡水电站泄洪洞底拱混凝土滑模施工技术

Concrete Slipform Construction for the Invert of Spillway Tunnel in Nuozhadu Hydropower Station

张尹耀 1李文瑛 1宋希宁1

作者信息

  • 1. 中国人民武装警察部队水电第一总队第一支队,河北唐山063004
  • 折叠

摘要

Abstract

The concrete in the invert of circular pressured sections of the spillway tunnel in Nuozhadu Hydropower Station was placed by using slipform. Following the requirements of construction specifications and managing strictly the construction according to construction program and quality standards, the construction period is shorten on the basis of guarantying the quality. The construction also provides a good basis for the concrete placement of other parts of tunnel, and achieves good economic and social benefits.

关键词

泄洪洞/底拱/滑模/糯扎渡水电站

Key words

spillway tunnel/ invert/ slipform/ Nuozhadu Hydropower Station