| 注册
首页|期刊导航|铀矿冶|空气间隔装药结构在某铀矿井分区接顶工艺中的应用

空气间隔装药结构在某铀矿井分区接顶工艺中的应用

高永学 寇子顺 李羽

铀矿冶2011,Vol.30Issue(3):120-123,4.
铀矿冶2011,Vol.30Issue(3):120-123,4.

空气间隔装药结构在某铀矿井分区接顶工艺中的应用

Application of charging structure with air space to stope roof-contacted technique in a uranium mine

高永学 1寇子顺 2李羽2

作者信息

  • 1. 中核浙江衢州铀业有限责任公司,浙江衢州,324008
  • 2. 核工业北京化工冶金研究院,北京,101149
  • 折叠

摘要

Abstract

Aimed at the potential safety hazards in using stope roof-contacted technique for hydraulic filling with tailings at No. 2 mining area of -135 level in a uranium mine, and based on research results and experiences on charging structure with air space at home and abroad,the charging technique with air space was first adopted in roof-contact of the stope, and good results were achived.

关键词

空气间隔装药结构/水力尾渣充填/分区接顶/爆破效果

Key words

charging structure with air space/hydraulic filling with tailings/stope roof-contact/blasting effect

分类

矿山工程

引用本文复制引用

高永学,寇子顺,李羽..空气间隔装药结构在某铀矿井分区接顶工艺中的应用[J].铀矿冶,2011,30(3):120-123,4.

铀矿冶

OACSTPCD

1000-8063

访问量0
|
下载量0
段落导航相关论文