铁道标准设计Issue(10):99-102,4.
包西铁路洞子崖隧道断层破碎带浅埋偏压段施工数值模拟分析
Simulation Analysis on the Construction of the Unevenly Pressured Shallow Section in Fault Fracture Zone of Dongziya Tunnel on Baotou-Xi'an Railway
林裕1
作者信息
- 1. 中铁隧道勘测设计院有限公司厦门分公司,福建厦门 361003
- 折叠
摘要
Abstract
Section DK683+938 ~ DK684+004 of Dongziya tunnel belongs to shallow uneven pressured tunnel with large section and passes through fault fracture zone. The project adopted common excavation methods including triple-bench with reserved core method, CRD method and two side heading method. In this paper, the numerical simulation results of three excavation methods were compared by using Flac 5. 0 software, and it has been concluded that two side headings excavation with the shallow side heading excavated first could effectively control tunnel periphery displacements, which ensured engineering quality and construction safety.关键词
铁路隧道/断层破碎带/浅埋偏压隧道/施工/数值模拟Key words
Railway tunnel/ Fault fracture zone/ Shallow buried and unevenly pressured tunnel/ Construction/ Simulation analysis分类
交通工程引用本文复制引用
林裕..包西铁路洞子崖隧道断层破碎带浅埋偏压段施工数值模拟分析[J].铁道标准设计,2011,(10):99-102,4.