Abstract

Though shield tunneling for subway construction has many advantages such as high degree of automation, fast construction progress and minor effects on buildings, yet some sections that shield can not pass through directly, such as hard rock stratum and pile foundation for building and bridges, are generally excavated by mining method and then let shield get through. In this article, based on the tunnel construction of Huangbeiling station to Xinxiu station section in east extending Line 2 of Shenzhen subway, introduces construction method without guide platform, with concrete, mortar, earth and stone backfilled and shield passing through the excavated section with mining method.

关键词

地铁隧道/盾构/矿山法/施工

Key words

Subway tunnel/ Shield/ Mining method/ Construction