摘要

Abstract

Combining with the # 1 and # 2 CFB boiler already operated in Inner Monglia Jinghai Coal gangue Power Plante. This paper analyzes the structure of coordinated control system, and related control scheme and logic relation is presented,and introduces the methods to deal with the challenging long delay and high order inertia control. The frequency regulation has been mentioned; The press deviation dragging load loop has been designed in order to limit the response speed of turbine valve) The Indirect Energy Balance ( IEB) strategy and Fuel feedforward has been used. On-site experiments in dicate that all the designed logic on CCS are effective and the control effects of CCS are ideal.

关键词

CFB锅炉/CCS/间接能量平衡/前馈

Key words

CFB boiler/CCS/Indirect Energy Balance ( IEB)/ feedforward