河北工程技术高等专科学校学报Issue(3):55-57,3.
一起操作箱与断路器配合不当引起的故障分析
Analysis of Fault Caused by Mismatch of Operation Box and Breaker
摘要
Abstract
According to the burnout of phase B closing self-holding plug-in of switch operation box in a substation in Cangzhou area, the paper briefly analyzed the problems on match of opening and closing mechanisms, operation box and inner switch control circuit, and put forward the technique solution of the problems.关键词
合闸线圈/操作箱/线圈铁芯行程/熔断时限/限流电阻Key words
closing coil/operation box/coil iron core stroke/fusing duration/current-limiting resistance分类
信息技术与安全科学引用本文复制引用
和滨..一起操作箱与断路器配合不当引起的故障分析[J].河北工程技术高等专科学校学报,2011,(3):55-57,3.