| 注册
首页|期刊导航|水力发电|积石峡水电站导流洞交叉段开挖支护施工技术

积石峡水电站导流洞交叉段开挖支护施工技术

苏晓军

水力发电2011,Vol.37Issue(11):54-56,3.
水力发电2011,Vol.37Issue(11):54-56,3.

积石峡水电站导流洞交叉段开挖支护施工技术

Construction Technologies for Excavating Cross Section of Diversion Tunnel in Jishixia Hydropower Station

苏晓军1

作者信息

  • 1. 黄河上游水电开发有限责任公司工程建设分公司,青海西宁810000
  • 折叠

摘要

Abstract

As the complex geological condition, diverse cross-section shape, bigger span and larger height difference in the cross section area of diversion tunnel and spillway tunnel in Jishixia Hydropower Station project, the engineering safety is significant. For guaranteeing the safe construction, the excavation and support program, including sub-sequence excavation and spraying plain concrete, anchor rode and pre-stressed anchorage cable supporting, are determined after numerical analysis of surrounding rock stability. The program is strictly implemented in practice without safety incident, and show that it is feasible and effective.

关键词

导流洞/交叉段/开挖/支护/施工技术/积石峡水电站工程

Key words

diversion tunnel/ cross section/ excavation/ support/ construction technology/ Jishixia Hydropower Station Projec