| 注册
首页|期刊导航|水力发电|泸定水电站大坝填筑的特殊问题及解决办法

泸定水电站大坝填筑的特殊问题及解决办法

李明辉 杨作才

水力发电2012,Vol.38Issue(1):41-43,3.
水力发电2012,Vol.38Issue(1):41-43,3.

泸定水电站大坝填筑的特殊问题及解决办法

Special Issues and Its Solutions in the Filling of Luding Dam

李明辉 1杨作才1

作者信息

  • 1. 中国人民武装警察部队水电第三总队第九支队,四川成都611130
  • 折叠

摘要

Abstract

Some special issues are encountered in the construction of Luding Dam, including the interference of gallery concrete pouring and dam filling, the dam filling being delayed by gallery construction, upstream and downstream impervious material transport through core wall, and how to ensure the quality of construction not affecting by the temporary rise of some dam section. Through reasonable layout, partition filling, laying temporary road to across the impervious body, and treating joints by slope cutting, these issues are solved, the safety of dam and flood control are guaranteed, and the progress, quality and benefits of dam construction are also ensured.

关键词

大坝填筑/特殊问题/泸定水电站

Key words

dam filling/ special issue/ Luding Hydropower Station

分类

建筑与水利

引用本文复制引用

李明辉,杨作才..泸定水电站大坝填筑的特殊问题及解决办法[J].水力发电,2012,38(1):41-43,3.

水力发电

OA北大核心CSTPCD

0559-9342

访问量0
|
下载量0
段落导航相关论文