Whole construction process real-time schedule control and visual analysis of the long distance diversion tunnel based on simulation

胡连兴 1佟大威 1焦凯2

作者信息

  • 1. 天津大学水利工程仿真与安全国家重点实验室,天津300072
  • 2. 二滩水电开发有限责任公司,成都610021
  • 折叠

摘要

Abstract

Long diversion tunnel is often featured by great embedded depth, long tunnel line, large hole diameter and extremely complicated geologic conditions. The engineering quantity of each process is large, and the influence is enormous; therefore, the internal and external environment and constraint condition are changed in the actual construction, leading to the deviation between formerly construction schedule plan and actual construction schedule plan. If the deviation isn' t corrected timely, the formerly plan can not guide the actual construction. In this paper, using computer simulation technology, control theory and virtual reality technology, the whole construction process real-time schedule control and visual analysis of the long distance diversion tunnel based on simulation are proposed. The feasibility study and scientific basis is provided for the real-time control of construction schedule.

关键词

长距离引水隧洞/施工进度/实时控制/可视化/仿真

Key words

long diversion tunnel/ construction schedule/ real-time control/ visual/ simulation

分类

建筑与水利

引用本文复制引用

胡连兴,佟大威,焦凯..基于仿真的长距离引水隧洞施工全过程进度实时控制与可视化分析研究[J].中国工程科学,2011,13(12):97-102,6.

基金项目

国家自然科学基金(90815019) (90815019)

国家自然科学基金创新研究群体科学基金(51021004) (51021004)

"十二五"国家科技支撑计划(2011BAB10B06) (2011BAB10B06)

中国工程科学

OA北大核心CSTPCD

1009-1742

访问量0
|
下载量0
段落导航相关论文