This article first elaborates the large ball mill system' s mechanical electricity and the control composition: water resistor cabinet, neutral point cabinet, synchronous motor excitation cubicle, the high - pressured voltage dropping starts,ball mill initial lubrication the high and low pressure oil station, the air operated coupling,ball mill temperature monitoring and the system interconnection PLC control cubicle. In view of its complex electricity and the control system, the article multianalysis its each constituent' s function and the logical relation,each kind of question which existed to the systems operation in carry on the detailed analysis to induce and to reorganize, proposed that solved these question specific measures and the method,optimized its electric control system, after implementation has made the good re-sult, has brought the more economic efficiency for the enterprise.关键词
球磨机/电气控制系统/优化Key words
ball mill/ electric control system/ optimization分类
信息技术与安全科学