水力发电2012,Vol.38Issue(3):31-33,3.
吉沙水电站勘测设计及体会
Survey and Design of Jisha Hydropower Station and Its Experiences
吴义航 1邓毅国 1掌于昶 1张红梅1
作者信息
- 1. 中国水电顾问集团北京勘测设计研究院,北京100024
- 折叠
摘要
Abstract
Jisha Hydropower Station is a diversion type project, in which, the total length of diversion system is 15.58 km. The rated head is 485 m and the maximum head is 540 m. The station installs two Pelton units with a unit capacity of 60 MW. The project design ideas are introduced herein from the aspects of head structure layout, diversion system alignment selection, powerhouse layout and unit type selection. The design can be as references to similar projects.关键词
枢纽布置/长引水隧洞/厂房布置/冲击式机组/吉沙水电站Key words
project layout/long diversion tunnel/powerhouse layout/Pelton unit/Jisha Hydropower Station分类
建筑与水利引用本文复制引用
吴义航,邓毅国,掌于昶,张红梅..吉沙水电站勘测设计及体会[J].水力发电,2012,38(3):31-33,3.