水力发电2012,Vol.38Issue(3):58-61,4.
吉沙水电站高压管道设计与施工
Design and Construction of the Penstock in Jisha Hydropower Station
高永辉 1张红梅1
作者信息
- 1. 中国水电顾问集团北京勘测设计研究院,北京100024
- 折叠
摘要
Abstract
The total length of diversion system in Jisha Hydropower Station is about 15.58 km. The rated head of station is 485.00 m and a penstock supplies water to two turbines. The high-pressure pipeline locates between the surge shaft and powerhouse and consists of a penstock, a bifurcation and two branches. The 1054 m-long penstock is designed to have a maximum internal water head of about 652.2m and is arranged in a way of the combination of horizontal and inclined sections. The exposed and buried penstock arrangements are compared, and different buried penstock schemes are also analyzed from the aspects of structure, economy and construction. Finally, an easy-constructed and economic buried penstock scheme is selected, in which the surrounding rock withstands no force.关键词
高压管道/明管/埋管/围岩分担受力/吉沙水电站Key words
high -pressure pipeline/exposed penstock/buried penstock/force sharing with surrounding rock/Jisha Hydropower Station分类
建筑与水利引用本文复制引用
高永辉,张红梅..吉沙水电站高压管道设计与施工[J].水力发电,2012,38(3):58-61,4.