中国电力2012,Vol.45Issue(1):10-14,5.
750kV系统及大电源接入对昌吉电网的影响
Impacts of the access of 750 kV system and super-power source on Changji power grid
周霄 1宋云亭 2田建设 1张志强 2李晶 2郝毅 3杨静3
作者信息
- 1. 华北电力大学,河北保定071003
- 2. 中国电力科学研究院,北京100192
- 3. 昌吉电业局,新疆昌吉831100
- 折叠
摘要
Abstract
Based on the development plan of UHV of State Grid Corporation of China and the planning grid of Changji in 2012, the current distribution, static security, transient stability, short circuit current level and power supply section of Changji grid after access of the 750 k V system and super-power source are analyzed. The short circuit current and transient stability of the planning grid for the year of 2015 are calculated too. The adaptability of the planning Changji grid is evaluated. The research results can provide advice in regional power network planning and operation.关键词
750kV系统/大电源/地区电网Key words
750 kV system/ super-power source/ regional power grid分类
信息技术与安全科学引用本文复制引用
周霄,宋云亭,田建设,张志强,李晶,郝毅,杨静..750kV系统及大电源接入对昌吉电网的影响[J].中国电力,2012,45(1):10-14,5.