Abstract
The second-phase concrete of overflow weir of the flood discharge and sediment gates in the lower reservoir of Pushihe Pumped-storage Power Station appears cracks. The cracks are treated by chemical grouting. The coring tests of the 14*. 29* and 37* crack show that there is no defect on the appearances of core samples, and the chemical grouting material fills the crack in a good condition and closely bonds with concrete. The effect of chemical grouting meets the requirements.关键词
化学灌浆/应用/蒲石河抽水蓄能电站Key words
chemical grouting/ application/ Pushihe Pumped-storage Power Station分类
建筑与水利引用本文复制引用
胡鑫,龙思佳,杜丹晨,赫岩松,孟玲,杨凯..化学灌浆工艺在蒲石河抽水蓄能电站中的应用[J].水力发电,2012,38(5):57-58,83,3.