水力发电学报2012,Vol.31Issue(1):93-98,6.
软基上大型泵站及基础抗震关键技术研究
Study on key aseismic technology of large-scale pumping station and its base on soft foundation
张燎军 1郭连琴 1李龙仲 1白莉萍 2许明德 2张洋2
作者信息
- 1. 河海大学水利水电学院,南京210098
- 2. 徐州市水利建筑设计研究院,江苏徐州221002
- 折叠
摘要
Abstract
A full 3D finite-element aseismic analysis model is developed for foundation-pumping station structure of Suining pumping station II of the east route south-to-north water transfer project,a large-scale pumping station on soft foundation in a meizoseismal area.Through analysis of computations and comparison of alternative schemes,a reinforcing scheme that adopts underground continuous wall foundation of an integral structure layout and anchor bolts-bored piles,is recommended,and a scheme of prestressed anchor bolts being tensioned at the construction stage is proposed to ensure stability of the deep foundation pit.The prestress of anchor bolts will be released after completion of the construction,so that the whole pumping station,maintenance room,control room and underground continuous wall can form a similar half-buried underground structure.Thus the key aseismic technical problems of this pumping station are completely resolved,and the proposed methods and results provide a technical support to the aseismic design of Suining pumping Ⅱ and the other pumping stations with soft foundation.关键词
水工结构/结构及基础抗震/ADINA/睢宁二站/南水北调东线工程/地下连续墙/灌注桩加锚杆Key words
hydraulic structure/seismic resistance of structure and foundation/ADINA/Suining pumping station/east route south-to-north water transfer project/underground continuous wall/bored pile with anchor bolts分类
建筑与水利引用本文复制引用
张燎军,郭连琴,李龙仲,白莉萍,许明德,张洋..软基上大型泵站及基础抗震关键技术研究[J].水力发电学报,2012,31(1):93-98,6.