高水头大流量岸边溢洪道窄缝消能工研究与实践

王才欢 侯冬梅 王思莹 李利

水力发电学报2012,Vol.31Issue(1):123-128,139,7.
水力发电学报2012,Vol.31Issue(1):123-128,139,7.

高水头大流量岸边溢洪道窄缝消能工研究与实践

Research and practice on narrow-slot energy dissipators of high-head and large-flood bank spillway

王才欢 1侯冬梅 1王思莹 1李利1

作者信息

  • 1. 长江水利委员会长江科学院,武汉430010
  • 折叠

摘要

Abstract

Shuibuya dam is the highest rockfill dam in the world at present and it adopts bank spillway for flood releasing.The design and construction of this spillway have to overcome several difficulties related to its large capacity and high drop of flood,narrow river valley,weak bedrock,large volumes of landslide on the two banks,and interference to energy dissipation by the nearby tail water of underground power station.Through a systematic test on hydraulic models,satisfactory solutions have been found to the problems of flood releasing and energy dissipation of large-scale bank spillway under the complex conditions,including silt control in the tail water region.Results of several research findings have been implemented on this project.Operation experiences of the project show that the narrow-slot dissipator and silt control method meet the design goals.The research results are useful to other similar projects.

关键词

水力学/岸边溢洪道/窄缝消能工/电站尾水淤积/模型试验/原型泄洪

Key words

hydraulics/bank spillway/narrow-slot energy dissipator/deposition of power station tail water/model experiment/prototype flood discharge