Abstract

The processing system of filter material and gravel mixed rock material for the construction of rockfill dam with core-wall of Nuozhadu Hydropower Station is just self-designed, installed and operated by our general team; of which some key techniques and technological procedures are initially dialed in the same sector. Therefore, the system is stable, scientific and perfect and then can meet the requirement of the dam filling construction.

关键词

反滤料/掺砾石料/加工系统/工艺流程/设备选型

Key words

filter material/gravel mixed rock material/processing system/technological procedure/equipment selection