路基工程Issue(3):121-123,126,4.
白土山隧道台阶法施工数值模拟研究
Numerical Simulation Study on Benching Construction at Baitushan Tunnel
张广乾 1李军胜 1李国辉1
作者信息
- 1. 内蒙古铁道勘察设计院有限公司,呼和浩特010050
- 折叠
摘要
Abstract
Combined with benching construction (temporary transverse support) at the entrance of Baitushan Tunnel. the displacement of the surroundina rock and the mechanical properties of the support structure in such construction at the large-section tunnel entrance are simulated with finite element numerical analysis. Through the analysis on the calculating results, the safety and rationality of this method is recognized offering basis for the design and implementation.关键词
铁路隧道/洞口段/台阶法(临时横撑)/数值模拟Key words
railway tunnel/entrance/benching construction (temporary transverse support )/numericalsimulation分类
交通工程引用本文复制引用