南水北调与水利科技2012,Vol.10Issue(3):154-156,141,4.DOI:10.3724/SP.J.1201.2012.03154
高淹没度开敞式水闸孔径计算公式探讨
Discussion of the Computational Formula for the Gate Size of Open Sluice with High Submergence Degree
贾西斌1
作者信息
- 1. 河南省水利勘测设计研究有限公司,郑州450016
- 折叠
摘要
Abstract
For the open sluice with a high submergence degree,the equation of (A. 0. 1-1) in the Design Specification for Sluice (SL265-2001) results in the unreasonable results. Based on the formula, the calculated gate width is small and the calculated conveyance capacity is too large. It is suggested that the equation of (A. 0. 2-1) is better applied when the submergence degree, h,/H0 ,is in the range of 0. 90 to 0. 95. When the submergence degree,h5Ho, is higher than 0. 95, the equation (A. 0. 2-1) should be used. Otherwise, the calculations of the designed gate widths are relatively small and the actual upstream banked-up water depths are high if other equations are used.关键词
宽顶堰/水闸孔径/高淹没度/淹没系数Key words
broad-crested weir/gate size/high submergence degree/submergence coefficient分类
建筑与水利引用本文复制引用
贾西斌..高淹没度开敞式水闸孔径计算公式探讨[J].南水北调与水利科技,2012,10(3):154-156,141,4.