西服生产流水线的时间管理OA北大核心CSTPCD
The time management about suit sewing process
采用观察法测量某西服企业生产流水线工时,从流水线的生产节拍和流水线的平衡率两指标对测量结果进行分析.结果认为,该企业西服生产的瓶颈工序节拍比较大,生产流水线的平衡率很低.针对问题,对西服生产流水线的时间管理提出了改进措施.对此可以考虑通过人员的调配,缝制工序的编排优化来提高生产效率.西服生产企业也可考虑测其他款式的西服生产时间,进行数据积累,从而提高西服生产线管理水平.
This study adopts observational method to measure the time consumption of suit sewing process, the measuring result have been analyzed in aspects of the producing beat and balance rate of assembly lines. It finds that the bottleneck beat of producing suits is long and balance rate of assembly lines is low at the enterprise. To solve these problems, the improvement measures for the time management of assembly lines for suits are discussed. Aiming at the probl…查看全部>>
刘雪林;陈雁;陈洪倩;丁佳
苏州大学纺织与服装工程学院,江苏苏州215021苏州大学纺织与服装工程学院,江苏苏州215021苏州大学纺织与服装工程学院,江苏苏州215021苏州大学纺织与服装工程学院,江苏苏州215021
轻工纺织
西服工时测量流水线平衡时间管理
Suit Time measurement Balance of assembly lines Time management
《丝绸》 2012 (6)
36-40,5