水利水电技术2012,Vol.43Issue(6):63-66,4.
全断面掘进机(TBM)施工中豆砾石回填灌浆技术
Pea-gravel backfill grouting technology during TBM construction
刘丽萍1
作者信息
- 1. 山西省万家寨引黄工程管理局,山西太原030012
- 折叠
摘要
Abstract
In accordance with the problems from the pea-gravel backfill grouting during TBM construction, a construction technology of section construction with inflation hose is put forward in combination with the conventional technologies concerned Hie technical details and specific measures of the technology are described herein. The practice demonstrates that the technology has the merits of convenient for construction, better effect of backfill grouting and lower construction cost and has been applied to the actual project, and then can ensure the safety operation of the long-distance water conveyance tunnel project关键词
全断面掘进机/豆砾石/回填灌浆/分段施工/万家寨引黄工程Key words
TBM/ pea-gravel/ backfill grouting/ section construction/ Wanjiazhai Yellow River Diversion Project分类
交通工程引用本文复制引用
刘丽萍..全断面掘进机(TBM)施工中豆砾石回填灌浆技术[J].水利水电技术,2012,43(6):63-66,4.