| 注册
首页|期刊导航|铁道标准设计|严寒地区无砟轨道CA砂浆施工工艺

严寒地区无砟轨道CA砂浆施工工艺

倪俊 黄跃东

铁道标准设计Issue(5):48-51,4.
铁道标准设计Issue(5):48-51,4.

严寒地区无砟轨道CA砂浆施工工艺

Processes of CA Mortar Grouting for Ballastless Track Slab in Cold Area

倪俊 1黄跃东1

作者信息

  • 1. 中铁八局集团第四工程集团有限公司,成都610051
  • 折叠

摘要

Abstract

The mixing ratio and construction processes for CA mortar grouting for ballastless slab track in cold area are proposed according to technical indexes, material teat and site construction process comparison so as to meet the requirements stipulated in Interim Technical Conditions for CRTS I Slab Ballastless Track Cement Emulsified Asphalt Mortar for Passenger Dedicated Railway and Technical Conditions for CRTS I Slab Ballastless Track Cement Emulsified Asphalt Mortar for Passenger Dedicated Railway-Supplementary Provisions for Cold Area. Future study is proposed on I slab ballastless track construction in cold area.

关键词

哈大客运专线/严寒地区/无砟轨道/CA砂浆/施工配合比/抗冻性

Key words

Harbin - Dalian Passenger Dedicated Line/ Cold area/ Ballastless track/ CA mortar/ Construction mixing ratio/ Anti-freezing

分类

交通工程

引用本文复制引用

倪俊,黄跃东..严寒地区无砟轨道CA砂浆施工工艺[J].铁道标准设计,2012,(5):48-51,4.

铁道标准设计

OA北大核心CSTPCD

1004-2954

访问量0
|
下载量0
段落导航相关论文