Abstract
The mixing ratio and construction processes for CA mortar grouting for ballastless slab track in cold area are proposed according to technical indexes, material teat and site construction process comparison so as to meet the requirements stipulated in Interim Technical Conditions for CRTS I Slab Ballastless Track Cement Emulsified Asphalt Mortar for Passenger Dedicated Railway and Technical Conditions for CRTS I Slab Ballastless Track Cement Emulsified Asphalt Mortar for Passenger Dedicated Railway-Supplementary Provisions for Cold Area. Future study is proposed on I slab ballastless track construction in cold area.关键词
哈大客运专线/严寒地区/无砟轨道/CA砂浆/施工配合比/抗冻性Key words
Harbin - Dalian Passenger Dedicated Line/ Cold area/ Ballastless track/ CA mortar/ Construction mixing ratio/ Anti-freezing分类