水资源与水工程学报2012,Vol.23Issue(3):41-43,47,4.
带狭长型上室的埋藏式调压井开挖施工技术研究
Study on excavation construction technology of buried surge shaft with long-narrow upper chamber
摘要
Abstract
The site of Bulunkou -Konggur hydropower station is located in high altitude area. The construction of buried surge shaft with long - narrow upper chamber is very difficult and exists many unsafe factors. Throughout technology study and innovation, the construction method of pilot shaft expanding excavation by stages is successfully used. The excavation construction of surge shaft is implemented smoothly while its security, quality, schedule and economical are satisfied.关键词
高海拔区/埋藏式/调压井/开挖施工Key words
high altitude area/ buried/ surge shaft/ excavation construction分类
建筑与水利引用本文复制引用
周峰,白现军,刘章,陈功民,侍克斌..带狭长型上室的埋藏式调压井开挖施工技术研究[J].水资源与水工程学报,2012,23(3):41-43,47,4.基金项目
国家高等学校博士点专项科研基金资助课题(200807580007) (200807580007)
新疆水利水电工程重点学科基金资助项目(xjzdxk-2010-10-06) (xjzdxk-2010-10-06)