摘要
Abstract
According to the statistics and analysis of the defects of Ertan Hydropower Station's 500 kV gas insulated switchgear (GIS) occurred in the past 12 years, the main types of the defects and their incidences are summarized. Accordingly, some preventive measures are provided, such as adopting advanced and maintenance-free equipment, improving maintenance process and quality of equipment, and so on. In addition, the methods for effectively finding defects and reducing defect incidence are discussed.关键词
GIS/缺陷分析/运行稳定/缺陷管理Key words
gas insulated switchgear/ defect analysis/ stable operation/ defect management分类