锦屏一级水电站拱坝施工进度仿真分析与方案比选OA北大核心CSCDCSTPCD
Simulation analysis and scheme comparison on construction progress of arch dam for Jinping I Hydropower Station
针对锦屏一级水电站拱坝坝体混凝土施工,系统分析了混凝土浇筑缆机数量、浇筑层升层高度和层间间隔时间与施工进度之间的关系,仿真分析了坝体施工进度、混凝土浇筑强度、机械设备效率等工程控制性参数,对大坝混凝土施工方案进行了比选,合理安排了坝块浇筑顺序,以便实现工程的计划工期.
For the concrete construction of the arch dam for Jinping I Hydropower Station, the relationships among the amount of cable conveyors, the height of concrete Hit and the time interval between lifts are systematically analyzed, and then a simulation analysis is made on the construction control parameters, such as the construction progress of the dam, the concrete placement intensity, the efficiency of mechanical equipment, etc. , furthermore, a comparison is …查看全部>>
宋凤莲;刘全;吴旭
武汉大学动力与机械学院,湖北武汉430072武汉大学水利水电学院,湖北武汉430072中国水利水电第七工程局有限公司,四川成都610081
水利科学
混凝土施工施工进度机械设备系统仿真拱坝锦屏一级水电站
concrete construction construction progress mechanical equipment system simulation arch dam Jinping I Hydropower Station
《水利水电技术》 2012 (7)
64-68,5