Abstract
The static frequency converter (SFC) of integrated gasification combined cycle (IGCC) is elaborated, taking the gas turbine project of Tianjing Hua-neng IGCC Power Station as an example, and the operating principle, process and characteristics of FSC are analyzed to provide a debugging guidence for the variable frequency starting-up of grand IGCC power station. The problems possibly occurring in the synchronization System of the gas turbine generator set is also analyzed and the logic of the synchronization system is discussed on the basis of the experiment record in the debugging process of gas turbine generator set. The modification suggestion is presented so as to achieve better cooperation of SFC and synchronization system.关键词
燃机/静态变频启动装置/同期系统/IGCCKey words
gas turbine generator/ static frequency converter/ synchronization system/ IGCC分类
信息技术与安全科学引用本文复制引用
牛利涛,刘晓航,洪海程..大型IGCC电站燃机变频启动特性的研究[J].现代电子技术,2012,35(18):188-191,4.