| 注册
首页|期刊导航|水力发电|盖下坝水电站施工期温度应力及损伤仿真分析

盖下坝水电站施工期温度应力及损伤仿真分析

徐闯 朱为玄 邓爱民 孙伟伟

水力发电2012,Vol.38Issue(10):47-49,3.
水力发电2012,Vol.38Issue(10):47-49,3.

盖下坝水电站施工期温度应力及损伤仿真分析

Simulation on Thermal Stress and Damage of Gaixiaba Dam during Construction Period

徐闯 1朱为玄 1邓爱民 1孙伟伟1

作者信息

  • 1. 河海大学力学与材料学院,江苏南京210098
  • 折叠

摘要

Abstract

According to the actual pouring of Gaixiaba Arch Dam, the three-dimensional thermal and stress fields of dam during whole construction period are simulated by using ANSYS and its secondary developed programs, and the maximum temperature and thermal stress are obtained. At the same time, the damage status of dam is also simulated by self-developed damage finite element program, and the damage fields of dam in some key construction moments are achieved. The simulations show that the thermal stress of dam is much less than the design allowable value and the damage value is smaller after implementing reasonable temperature control measures, and the dam will not appear macro crack during construction period.

关键词

拱坝/温度场/应力场/损伤场/盖下坝水电站

Key words

arch dam/ temperature field/ stress field/ damage field/ Gaixiaba Hydropower Station

分类

建筑与水利

引用本文复制引用

徐闯,朱为玄,邓爱民,孙伟伟..盖下坝水电站施工期温度应力及损伤仿真分析[J].水力发电,2012,38(10):47-49,3.

基金项目

国家自然科学基金资助项目(10972072, 50878077) (10972072, 50878077)

水力发电

OA北大核心CSTPCD

0559-9342

访问量0
|