首页|期刊导航|长江科学院院报|六凤山水库50 m高土坝的防渗设计与施工

六凤山水库50 m高土坝的防渗设计与施工

蔡联华

长江科学院院报2012,Vol.29Issue(9):64-68,73,6.
长江科学院院报2012,Vol.29Issue(9):64-68,73,6.DOI:10.3969/j.issn.1001-5485.2012.09.015

六凤山水库50 m高土坝的防渗设计与施工

Design and Construction of Seepage Control for the 50m-High Earth Dam of Liufengshan Reservoir

蔡联华1

作者信息

  • 1. 钦州市水利电力勘测设计院,广西钦州535000
  • 折叠

摘要

Abstract

In the reinforcement design for Liufengshan Reservoir dam, the tallest earth dam in Guangxi , we selected a seepage control scheme of plastic concrete core wall in the light of the engineering geological conditions and characteristics of the earth dam. Moreover, inadequate filling compaction quality and large sand content of the dam usually resulted in hole collapses during the construction of the impermeable plastic concrete core wall. We adopted a series of countermeasures, including increasing the slurry' s density and adding sawdust in the slurry, filling grouting, and high-pressure rotary jet grouting. In addition, we described the construction program of plastic concrete core wall and the selection of construction machinery used in the project. It could be taken as reference for similar projects.

关键词

土坝/防渗设计/塑性砼心墙施工/塌孔处理

Key words

earth dam/ seepage control design/ construction of plastic concrete core wall/ treatment of hole collapse

分类

建筑与水利

引用本文复制引用

蔡联华..六凤山水库50 m高土坝的防渗设计与施工[J].长江科学院院报,2012,29(9):64-68,73,6.