水力发电2012,Vol.38Issue(11):56-58,3.
阿海水电站大坝混凝土施工方案优化
Optimization on Dam Concrete Construction Scheme of Ahai Hydropower Station
赵正平1
作者信息
- 1. 中国水利水电第三工程局有限公司,陕西西安710016
- 折叠
摘要
Abstract
As limited by a variety of factors, the dam construction of Ahai Hydropower Station in earlier stage is lagged more than 2 months. For achieving the goal of reservoir impoundment in December 2012, some optimized measures are taken in concrete construction of dam. These optimizations have effectively accelerated the construction, and guarantee the quality. The adoption of dump trucks to directly dump roller梒ompacted concrete on pouring surface is the key to ensure construction progress and quality.关键词
大坝混凝土/施工/方案优化/施工进度/阿海水电站Key words
dam concrete/construction/scheme optimization/construction progress/Ahai Hydropower Station分类
建筑与水利引用本文复制引用
赵正平..阿海水电站大坝混凝土施工方案优化[J].水力发电,2012,38(11):56-58,3.