电网技术2012,Vol.36Issue(12):250-255,6.
核电机组参与电网调峰的运行方式及效益分析
Operation Mode and Benefits of Nuclear Power Plant Participating in Peak Load Regulation of Power System
摘要
Abstract
Nuclear power plants have to be faced with urgent requirement of participating in peak load regulation of power grid. The peak load regulation performances of nuclear power plant (NPP) such as its power regulation characteristics, its enduring capability of long-term low-power operation and stretch-out operation characteristics were researched. Based on the calculation and analysis on peak load regulation cost and benefit of NPP, the location, criterion and peak balance algorithm of NPP participating in peak regulation were proposed, and the case based on actual power grid were calculated and analyzed. Results of the research show that NPP possesses better ability of peak load regulation and the cost is lower, so NPP can participate in daily- and weekly-peak load regulation and yearly load tracking, however the depth and speed of peak load regulation by NPP are restricted by security and economy. Properly participating in peak load regulation by NPP can improve both security and flexibility of power grid and enhance the efficiency of resource configuration.关键词
核电机组/调峰特性/运行方式/调峰成本/调峰平衡Key words
nuclear power plant/ peak load regulation characteristic/ operation mode/ cost of peak load regulation/balance of peak load regulation分类
信息技术与安全科学引用本文复制引用
赵洁,刘涤尘,杨楠,孙文涛,王强..核电机组参与电网调峰的运行方式及效益分析[J].电网技术,2012,36(12):250-255,6.基金项目
国家自然科学基金项目(51077103) (51077103)