基于NSGA-Ⅱ的模糊多目标产品开发项目调度
NSGA-Ⅱ based fuzzy multi-object product development project scheduling approach
摘要
Abstract
Aiming at the time and cost tradeoff problem in product development project scheduling with fuzzy durations, this paper considered the effect of decision -makers' risk preference on time and cost tradeoff in fuzzy environment further, and it introduced NSGA- Ⅱ to solve the problem in project example. The results show that by means of adjusting the values of risk acceptance level and optimism index, different Pareto sets are obtained, from which the decision can choose the preferred scheduling alternative.关键词
项目调度/模糊/工期—成本均衡/风险偏好/NSGA-ⅡKey words
project scheduling/ fuzzy/ time-cost tradeoff/ risk preference/ NSGA-Ⅱ分类