水利水电技术2013,Vol.44Issue(1):93-96,4.
Φ4700mm隧道二衬自密实混凝土全圆一次浇筑施工技术
Construction technology of whole-circle and one-time pouring of self-compacting concrete for secondary lining of tunnel of Φ4700 mm
孟学文 1李志强 1马继周1
作者信息
- 1. 北京市政建设集团第四工程处,北京100073
- 折叠
摘要
Abstract
Taking the secondary lining for tunnel of Φ4 700 mm in the No. 13 bid-section for the South Main Canal--an assistant project in Beijing for the South-to-North Water Transfer Project as an engineering case, the construction method for the whole-circle and one-time pouring of self-compacting concrete for the secondary lining inside of the shield-excavated tunnel is de-cribed herein; in which the impacts from both the self properties and the in situ pouring technology of the self-compacting concrete on the surface quality of the secondary lining of the tunnel is dissertated, and then the relevant countermeasures for how to reduce the conventional defects of the surface quality are summarized as well.关键词
隧道二衬/自密实混凝土/缺陷/对策/北京市南水北调配套工程/南干渠Key words
tunnel secondary lining/ self-compacting concrete/ defect/ countermeasure/ assistant project in Beijing for the South-to-North Water Transfer Project/ South Main Canal分类
建筑与水利引用本文复制引用
孟学文,李志强,马继周..Φ4700mm隧道二衬自密实混凝土全圆一次浇筑施工技术[J].水利水电技术,2013,44(1):93-96,4.