Abstract
The process of CPR1000 gaseous radwaste treatment system was introduced,and compared with the gaseous radwaste treatment technology in the 3 rd generation nuclear power plant.Then a concept to improve CPR1000 gaseous radwaste treatment system based on the new technology was put forward.Preliminary analysis showed that the improvement is feasible to be used in new plant design and inservice plant modification.关键词
放射性废气处理系统/废气/处理/活性碳延迟/CPR1000/AP1000Key words
gaseous radwaste treatment system/ waste gaseous/ treatment/ activated carbon delay/CPR1000 / AP1000分类
能源科技引用本文复制引用