乌江沙沱水电站水轮机选型分析
Selection Analysis for Turbine of Shatuo Hydropower Station in Wujiang River
高瑜 1赵明琴2
作者信息
- 1. 中国水电工程顾问集团公司,北京100120
- 2. 中国水电顾问集团贵阳勘测设计研究院,贵州贵阳550081
- 折叠
摘要
Abstract
The operation head of Shatuo Hydropower Station is between 50 m to 74.9 m.The blocked output of Station mostly occurs in flood season.By comprehensively considering the reduction of blocked output and the operation stability of turbine,five rated head schemes of 61,62.5,64,65.5,67 m are analyzed and compared.The economic and reasonable turbine parameters are finally proposed.关键词
水轮机选型/转轮/额定水头/沙沱水电站Key words
type selection for turbine/ runner/ rated head/ Shatuo Hydropower Station分类