Study on Operation Efficiency Improvement of Cable Cranes in the Construction of Tingzikou Water Control Project

夏大勇 1练柳君 2张辉1

作者信息

  • 1. 武汉大学,湖北武汉430072
  • 2. 嘉陵江亭子口水利水电开发有限公司,四川苍溪628400
  • 折叠

摘要

Abstract

Based on the operation characteristics of cable cranes in concrete pouring,the whole process of vehicle transportation and cable crane operation is disassembled and divided into nine operating units.Fifty samples are collected from each operating unit to count and analyze whole operation cycle of cable crane moving and concrete pouring.Though the data analysis,key processes which need to be improved are found,and six improvements are proposed to optimize cable crane operation.The new operation scheme of cable crane has improved working efficiency of about 20%.

关键词

缆机/工作研究/工作效率/混凝土浇筑/亭子口水利枢纽工程

Key words

cable crane/operation study/operation efficiency/concrere pouring/Tingzikou Water Control Project