溪洛渡水电站拱坝施工期坝基变形监测分析

胡长浩 周扬 兰溶 关容章

水力发电2013,Vol.39Issue(8):19-22,4.
水力发电2013,Vol.39Issue(8):19-22,4.

溪洛渡水电站拱坝施工期坝基变形监测分析

Analysis on Deformation Monitoring Data of Arch Dam Foundation of Xiluodu Hydropower Station during Construction Period

胡长浩 1周扬 1兰溶 1关容章1

作者信息

  • 1. 溪洛渡水力发电厂,云南永善657300
  • 折叠

摘要

Abstract

In order to understand the deformation and statue of arch dam foundation in Xiluodu Hydropower Station during construction,initial water storage and operation periods,the vertical and horizontal displacements of dam foundation are monitored and the monitoring data are preliminarily analyzed to keep dam safety and provide scientific basis for project management during construction and operation periods.The analyses show that the settlement of dam foundation is uniform and the variation complies with normal rules.

关键词

拱坝/坝基变形/施工期/溪洛渡水电站

Key words

arch dam/ dam foundation deformation/ construction period/ Xiluodu Hydropower Station