摘要

Abstract

  Governor is one of the major equipment of a hydropower station. Operation parameters of governor are di⁃rectly related to safety of power grid and quality of electric energy. Upgrade of governor can improve quality of pow⁃er grid. A summarization was made on the experience in governor commissioning and maintenance of 2nd-stage project of Manwan Hydropower Station.

关键词

调速器/调试/漫湾电厂

Key words

Governor/commissioning/Manwan Hydropower Station