摘要
Abstract
The theory and system constitution of selective catalytic reduction (SCR) denitrification technique are introduced in this pape. Taking a 600MW unit of a certain power plant in Diandong of China as an example, this paper elaborates on the commissioning process of the flue gas denitrification engineering of SCR, and then analyzes the key problems during the commissioning, which can be used as reference of similar denitrification project commissioning in the future.关键词
烟气脱硝/选择性催化还原技术(SCR)/工程调试/锅炉Key words
flue gas denitrification/selective catalytic reduction (SCR)/commissioning/boiler分类
信息技术与安全科学